There are a number of factors that could shift the timing of projects, causing them to be completed faster or slower than originally anticipated. Some of these factors are: public health concerns, opportunities to partner with others, the availability of grant or low-interest money, and the general construction climate. Please use this map with the understanding that the status of a given project is correct at the time of the last update.

Jonathan Drive

Reference "A"
This Reference is to Jonathan Lane. At this time there are no plans to install public sewer here.
Last updated January 27, 2014

Morwood Area

Reference "B"
Status: The Township is currently in the process of modifying its 537 Plan (this plan, once approved, becomes the basis for public sewer extension). The primary focus of this plan is the sewering of the Morwood area. Springshire may or may not be included in the Morwood extension.

Last updated June 14, 2016

Valley Sewer

Reference "C & D"
Status: All planned public sewer extensions have been completed on Allentown, Lower, Halteman, and Moyer Roads. Delp Road sewer installation is currently underway.
Last updated January 27, 2014

Mininger Road/Leslie Lane

Reference "E"
Status: This project is still planned but is not likely to occur within the next year.

Last updated January 27, 2014

Reliance & Cowpath

Reference "E"
Status: These few homes are in need of public sewer but this is unlikely to occur this year.

Last updated January 27, 2014

Forrest & Cowpath

Reference "G"
Status: The Authority is looking at completing this project in 2014.
Last updated January 27, 2014

County Line Road Area

Reference "H"
Phase I of the Sewer Management Program identified this area as needing public sewer. This project is being considered but no firm date has been established to start.
Last updated January 27, 2014

Moyer Road Area

Reference "I"
The SMP indicated that these properties on Moyer Road are in need of public sewer.
Last updated January 27, 2014

Kulp Road Area

Reference "J"
Public sewer for this area is on hold at this time.
Last updated January 27, 2014

Schoolhouse Road Area

Reference "K"
A sewer line is being installed to provide service to Amplifier Research. The line may then be extended to provide service to other properties along that portion of Schoolhouse Road.
Last updated January 27, 2014

Schoolhouse at Route 113

Reference "L" FSA hopes to complete construction of a sewer line along this section of Schoolhouse Road in 2014.
Last updated January 27, 2014

High St/Homestead Area

Reference "M"
The Authority received a number of requests from residents in this area to provide public sewer. In a survey, the majority of respondents wanted public sewer. At this time, with all of the other projects that the Authority has n the works it is unlikely that this area will receive public sewer for at least 3 to 5 years.
Last updated January 27, 2014

Allentown Rd./Rittenhouse Pl B

Reference "N"
This area around the intersection of Allentown and Indian Creek Roads (as well as Rittenhouse Place) is being reviewed along with Morwood in the Township’s updated 537 plan.
Last updated January 27, 2014

Morwood Rd. b/w Sunset & Bergey

Reference "O"
This sections of Morwood Road between Sunset and Bergey is currently under review for public sewer. It is possible that construction could begin in 2014.

Eisenhauer/Gerhart-Morwood Ph 2

Reference "P"
This area includes Keller Creamery, Indian Creek, Schoolhouse, Eisenhauer, Gerhart, and Crestwood. It is being reviewed along with Morwood in the Township’s updated 537 plan.
Last updated January 27, 2014

Meadowwood Lane

Reference "Q"
Numerous inquiries have been made regarding sewer for Meadow Wood Lane. The Township is considering this area in their 537 Plan update.
Last updated January 27, 2014